The City of Stephenville selected Provenance Engineering to provide design, bid and construction phase services for a new water supply program. As part of the overall program, a bid package that included rehab of the existing pump station, a new 4 MGD pump station, planning for a future pump station, a new 1 Million Gallon prestressed concrete ground storage tank, rehabilitation of the existing 1 MG concrete tank, new chlorine injection and monitoring, and new raw and finished water metering was developed.
PROJECT COMPONENTS:
- New 4 MGD Pump Station
- 1MG New Ground Storage Tank
- New chemical injection
- New influent and effluent flow metering
- Future Pump Station Planning