WWTP Improvements

City of Sherman

Project Details

Provenance Engineering provided design support and value engineering review of this renovation to the existing 8-MGD wastewater treatment plant improvements project. The project improvement was $7 million. Our team worked closely with the design engineering team to identify opportunities for operational improvements, cost savings and ways to expedite construction.

Challenges

The clarifiers had dome covers that had to be removed for improvements to take place. However, there was an overhead power line directly above the dome covers. Also, the original shutdown plan called for almost a dozen different shutdowns of the aeration basins to replace multiple gates that were frozen.

Solutions

Our team developed a solution to remove the domes without the cost of bringing in a large crane and lessen the risk of electrocution. Provenance also presented a solution that would reduce the number of required plant shutdowns during construction from 12 to two during the slide gate replacement.

Construction Value
$6.7MM

Our goal is to provide longevity in technical solutions and stability as an engineering provider that uniquely understands each clients’ needs and infrastructure.

Map of Texas

Our team has
performed projects
valued over

$2.5 Billion

In Construction for water & wastewater

Located in Dallas/Fort Worth, West Texas/Panhandle, and San Antonio