The City of Rio Vista selected Provenance Engineering to provide design, bid, and construction phase services for a wastewater treatment plant expansion. The first phase involved a conceptual-level study completed in just two months. Provenance presented findings to the Johnson County Commissioners Court on behalf of the City, successfully securing 75% of the estimated project cost in ARPA funds. The project includes a new headworks structure, a 300% increase in treatment capacity to meet growth demands, and upgrades to the existing processes and infrastructure. Provenance also evaluated future peak flow management and tertiary filtration options.
Project Components
- TCEQ Expansion Permitting
- $3 Million Grant
- New SBR Basins
- New Headworks
- New Solids Dewatering
- New Disinfection Basin
- Adding 300% of Additional Treatment Capacity
- Planning for Peak Flow Management
- Construction Inspection