Development of Water Supply System

Perkins (City of McKinney)

Project Details

Provenance Engineering provided technical design support and value engineering for a project encompassing a new 2-MGD high-service pump station, 200,000-gallon ground storage tank, two water supply wells, a hypochlorite disinfection system, an emergency generator, 1,750 feet of pipeline, and a metering station.

Project components: 
  • New 2-MGD High Service Pump Station
  • 200,000 Ground Storage Tank
  • Two Water Supply Wells
  • Hypochlorite Disinfection System
  • Emergency Generator
  • 1,750 feet of Pipeline
  • Metering Station

Challenges

The project was part of a $100M development with stringent regulatory compliance requirements and an aggressive schedule to meet the owner’s deadlines.

Solutions

Provenance Engineering collaborated with the design engineering team to identify operational improvements, implement cost-saving measures, and expedite construction. This strategic approach ensured compliance, enhanced efficiency, and helped the project stay on track to meet the owner’s timeline.

Construction Value
$3 Million

Our goal is to provide longevity in technical solutions and stability as an engineering provider that uniquely understands each clients’ needs and infrastructure.

Map of Texas

Our team has
performed projects
valued over

$5 Billion

In Construction for water & wastewater

Located in Dallas/Fort Worth, West Texas/Panhandle, and San Antonio