Provenance Engineering was hired to provide technical design support and value engineering for the project that included a new 2-MGD high service pump station, 200,000 ground storage tank, two water supply wells, hypochlorite disinfection system, emergency generator, 1,750 feet of pipeline, and metering station.
Challenges
The project was part of a large $100M development and faced regulatory compliance and aggressive schedule.
Solutions
Our team worked closely with the design engineering team to identify opportunities for operational improvements, cost savings and ways to expedite construction to meet the owner’s deadline.
Construction Value
$2,600,000Our goal is to provide longevity in technical solutions and stability as an engineering provider that uniquely understands each clients’ needs and infrastructure.
Our team has
performed projects
valued over
$2.5 Billion
In Construction for water & wastewater